Southwest Environmenta Limited were approached by a company based in woking whop had been manufacturing compost for 30 years, they had been operating under a local authority license for the activity but now they needed an environmental permit, owing the the environmental permitting regulation coming in to force.
Over a period of 3 months SWEL prepared and submitted the application which owing to the bespoke nature of the permit required and proximity of the site to various nature reserves and sensitive receptors was a labourious process.
Add caption |
The permit was granted after around 4 months.
Unfortionatly the environmental permitting regulations do not take in to account the benign nature of waste operations that have been taking place over 10’s of years with incident. For example despite having resdients living immediatly adjacent to site who had not complained of odours over the 30 year life span of the site, an odour managment plan was aked for, as was a Site Specific Bio-Aerosol Risk Assessment SSBRA.